Sign In

Select Site:
Key Documents:
Total Site Documents:
  
Document Title
  
  
  
4922-SRCO WWNA
Conditional Site Rehabilitation Completion Order (SRCO) for the Wastewater Neutralization Area. July 26, 2016
Regulatory DocumentFlorida7/29/2016
4921-SRCO_NE_Site_PIN
Conditional Site Rehabilitation Completion Order (SRCO) for the Northeast Site. July 26, 2016.
Regulatory DocumentFlorida7/29/2016
4941-N02300_4.5 ACRE Site SRCR_092019
Unconditional Site Rehabilitation Completion Order (SRCO) for the 4.5 Acre Site. September 16, 2019
Regulatory DocumentFlorida9/30/2019
44555_PIN_EnvMonRepBldg100_2023
Environmental Monitoring Annual Progress Report for the Building 100 Area at the Young - Rainey STAR Center June 2022 Through May 2023. LMS/PIN/44555 July 2023
Progress ReportFlorida7/12/2023
  
Document Title
  
  
  
44555_PIN_EnvMonRepBldg100_2023
Environmental Monitoring Annual Progress Report for the Building 100 Area at the Young - Rainey STAR Center June 2022 Through May 2023. LMS/PIN/44555 July 2023
Progress ReportFlorida7/12/2023
40817_PIN_Bldg100_Annual_Jun2021-May2022
Environmental Monitoring Annual Progress Report for the Building 100 Area at the Young - Rainey STAR Center June 2021 Through May 2022. LMS/PIN/40817 July 2022
Progress ReportFlorida7/31/2022
Southbrook DRC_recorded Inst 2022208800 Bk 22125 Pg 1618, Pinellas County, FL (01746972xBA9D6)
Declaration of Restrictive Covenant and Consent and Subordination of Mortgage to Declaration of Restrictive Covenant between Southbrook Corporate Center, LLC and Florida Department of Environmental Protection. July 6, 2022
Institutional ControlsFlorida7/21/2022
First Amendment to Non-Exclusive Easement recorded Inst. 2022208801 Bk 22125 Pg 1630, Pinellas County, FL (01746976xBA9D6)
First Amendment to a Non-Exclusive Access and Environmental Work Easement and Covenant to Restrict Use Agreement between Southbrook Corporate Center, LLC and U.S. Department of Energy. July 6, 2022
Institutional ControlsFlorida7/21/2022
N02377_PIN_DewatContingPlanSthbrk
Dewatering Contingency Plan for Southbrook Corporate Center, LLC at 10950 S. Belcher Road, Largo, Pinellas County, Florida. LMS/PIN/N02377-0.0 May 2022
Institutional ControlsFlorida5/31/2022
10-8-21 DOE Permit Final Issuance-DOE.Receipt
HSWA Corrective Action Permit 34170/005/HH October 8, 2021
Regulatory DocumentFlorida10/29/2021
School Board Agreement DE-RO01-21LM70286_fully_executed
Agreement between Pinellas County School Board and U.S. Department of Energy. DE-RO01-21LM70286 September 2021
Institutional ControlsFlorida9/30/2021
N02365_Bldg_100_Annual Jun2020-May2021
Environmental Monitoring Annual Progress Report for the Building 100 Area at the Young - Rainey STAR Center June 2020 Through May 2021. LMS/PIN/N02365 July 2021
Progress ReportFlorida7/31/2021
4943-Non-Exclusive Access and Environmental Work
Non-Exclusive Access and Environmental Work Easement and Covenant to Restrict Use Agreement between Southbrook Corporate Center, LLC and U.S. Department of Energy. August 26, 2020
Institutional ControlsFlorida8/28/2020
4942-N02326_Bldg 100_Annual Jun2019-May2020
Environmental Monitoring Annual Progress Report for the Building 100 Area at the Young - Rainey STAR Center June 2019 Through May 2020. LMS/PIN/N02326 July 2020
Progress ReportFlorida7/31/2020
4941-N02300_4.5 ACRE Site SRCR_092019
Unconditional Site Rehabilitation Completion Order (SRCO) for the 4.5 Acre Site. September 16, 2019
Regulatory DocumentFlorida9/30/2019
4939-N02303_PIN_Dec_May2019
Environmental Monitoring Semiannual Progress Report for the Building 100 Area at the Young - Rainey STAR Center December 2018 Through May 2019. LMS/PIN/N02303 June 2019
Progress ReportFlorida6/28/2019
8680-N02300_4.5 ACRE Site SRCR
Site Rehabilitation Completion Report with No Further Action Proposal for the 4.5 Acre Site. LMS/PIN/N02300 June 2019
Regulatory DocumentFlorida6/28/2019
4938-N02289_PIN_4thsamplingevent
4.5 Acre Site Fourth Closure-Monitoring Sampling Report, Pinellas County, Florida, Site. LMS/PIN/N02289 February 2019
Progress ReportFlorida2/28/2019
4936-N02275_PIN_Jun-Nov18
Building 100 Environmental Monitoring Semiannual Progress Report for the Young - Rainey STAR Center June Through November 2018. LMS/PIN/N02275 January 2019
Progress ReportFlorida1/31/2019
4937-N02284_PIN_3rdsampling event
4.5 Acre Site Third Closure-Monitoring Sampling Report, Pinellas County, Florida, Site. LMS/PIN/N02284 January 2019
Progress ReportFlorida1/30/2019
4935-N02274_2ndQtr_4_5Acre_ProgressReport
4.5 Acre Site Second Quarterly Sampling Report, Pinellas County, Florida, Site. LMS/PIN/N02274 December 2018
Progress ReportFlorida12/31/2018
4934-N02268_PIN_4_5Acre_ProgressReport
4.5 Acre Site First Quarterly Sampling Report, Pinellas County, Florida, Site. LMS/PIN/N02268 October 2018
Progress ReportFlorida10/31/2018
4929-N02237_PIN_Dec17-May18
Building 100 Environmental Monitoring Semiannual Progress Report for the Young - Rainey STAR Center December 2017 through May 2018. LMS/PIN/N02237 June 2018
Progress ReportFlorida6/29/2018
4930-N02238_PIN_4_5AcreDec17_May18
Semiannual Progress Report for the 4.5 Acre Site December 2017 through May 2018. LMS/PIN/N02238 June 2018
Progress ReportFlorida6/28/2018
4927-N02914_jun-nov17
Sitewide Environmental Monitoring Semiannual Progress Report for the Young - Rainey STAR Center June Through November 2017. LMS/PIN/N02914 January 2018
Progress ReportFlorida1/31/2018
4928-N02915_4_5Acre_jun-nov17
Semiannual Progress Report for the 4.5 Acre Site June Through November 2017. LMS/PIN/N02915 January 2018
Progress ReportFlorida1/30/2018
4926-N02159_PIN_dec16-may17
Sitewide Environmental Monitoring Semiannual Progress Report for the Young - Rainey STAR Center December 2016 Through May 2017. LMS/PIN/N02159 June 2017
Progress ReportFlorida6/30/2017
4925-N02160_PIN_4_5Acre_dec16-may17
Semiannual Progress Report for the 4.5 Acre Site December 2016 Through May 2017. LMS/PIN/N02160 June 2017
Progress ReportFlorida6/29/2017
4923-N02130_PIN_june-nov16
Sitewide Environmental Monitoring Semiannual Progress Report for the Young - Rainey STAR Center June Through November 2016. LMS/PIN/N02130 January 2017
Progress ReportFlorida1/31/2017
4924-N02131_PIN_4_5Acre_june-nov16
Semiannual Progress Report for the 4.5 Acre Site June Through November 2016. LMS/PIN/N02131 January 2017
Progress ReportFlorida1/30/2017
4922-SRCO WWNA
Conditional Site Rehabilitation Completion Order (SRCO) for the Wastewater Neutralization Area. July 26, 2016
Regulatory DocumentFlorida7/29/2016
4921-SRCO_NE_Site_PIN
Conditional Site Rehabilitation Completion Order (SRCO) for the Northeast Site. July 26, 2016.
Regulatory DocumentFlorida7/29/2016
4919-N02082_PIN
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center December 2015 Through May 2016. LMS/PIN/N02082 June 2016
Progress ReportFlorida6/30/2016
4920-N02083_PIN
Semiannual Progress Report for the 4.5 Acre Site December 2015 Through May 2016. LMS/PIN/N02083 June 2016
Progress ReportFlorida6/30/2016
4917-N02033_pin
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center June Through November 2015. LMS/PIN/N02033 December 2015
Progress ReportFlorida12/31/2015
4916-N02034_PIN
Semiannual Progress Report for the 4.5 Acre Site June Through November 2015. LMS/PIN/N02034 December 2015
Progress ReportFlorida12/30/2015
5034-MOA to Conduct Continuing Obligations_DOE_STARCenter
Memorandum of Agreement to Conduct Continuing Obligations between Pinellas County Economic Development Authority and U.S. Department of Energy. September 2015
Institutional ControlsFlorida9/30/2015
5037-Declaration of Restrictive Covenant_STAR Center Bldg 100_FDEP
Declaration of Restrictive Covenant Building 100 Solid Waste Management Units between Pinellas County Economic Development Authority and Florida Department of Environmental Protection. September 16, 2015.
Institutional ControlsFlorida9/30/2015
5038-Declaration of Restrictive Covenant_STAR Center NE Site_FDEP
Declaration of Restrictive Covenant Northeast Site Solid Waste Management Unit between Pinellas County Economic Development Authority and Florida Department of Environmental Protection. September 16, 2015
Institutional ControlsFlorida9/30/2015
5039-Declaration of Restrictive Covenant_STAR Center WWNA_FDEP
Declaration of Restrictive Covenant Wastewater Neutralization Area Solid Waste Management Unit between Pinellas County Economic Development Authority and Florida Department of Environmental Protection. September 16, 2015.
Institutional ControlsFlorida9/30/2015
4914-N01993_PIN
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center December 2014 Through May 2015. LMS/PIN/N01993 June 2015
Progress ReportFlorida6/30/2015
4915-N01994_PIN
Semiannual Progress Report for the 4.5 Acre Site December 2014 Through May 2015. LMS/PIN/N01994 June 2015
Progress ReportFlorida6/29/2015
5036-Declaration of Restrictive Covenant_BCH-1_FDEP
Declaration of Restrictive Covenant between BCH-1, LTD. and Florida Department of Environmental Protection. April 24, 2015
Institutional ControlsFlorida4/30/2015
4913-N01962_Sitewide semiannual June-Nov14
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center June Through November 2014. LMS/PIN/N01962 December 2014
Progress ReportFlorida12/31/2014
4912-N01963_4_5Acre Semiannual June-Nov14
Semiannual Progress Report for the 4.5 Acre Site June Through November 2014. LMS/PIN/N01963 December 2014
Progress ReportFlorida12/30/2014
4911-N01883_PIN
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center December 2013 Through May 2014. LMS/PIN/N01883 June 2014
Progress ReportFlorida6/30/2014
4910-N01884_PIN
Semiannual Progress Report for the 4.5 Acre Site December 2013 Through May 2014 LMS/PIN/N01884 June 2014
Progress ReportFlorida6/27/2014
5040-Declaration of Restrive Covenant_PinellasSchoolBoard_FDEP
Declaration of Restrictive Covenant between School Board of Pinellas County and Florida Department of Environmental Protection. May 20, 2014
Institutional ControlsFlorida5/30/2014
5035-Declaration of Restrictive Covenant_BankofTampa_FDEP
Declaration of Restrictive Covenant between Bank of Tampa and Florida Department of Environmental Protection. April 22, 2014
Institutional ControlsFlorida4/30/2014
4909-N01843_PIN
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center June Through November 2013. LMS/PIN/N01843 December 2013
Progress ReportFlorida12/30/2013
4908-N01844_PIN
Semiannual Progress Report for the 4.5 Acre Site June Through November 2013. LMS/PIN/N01844 December 2013
Progress ReportFlorida12/30/2013
5032-Easement, Covenant to Restrict Use_BankofTampa (Rally) _DOE
Easement, Covenant to Restrict Use and Access Agreement between Rally Stores Incorporated and U.S. Department of Energy. July 22, 2013
Institutional ControlsFlorida7/31/2013
5033-Easement, Covenant to Restrict Use_BCH-1_DOE
Easement, Covenant to Restrict Use and Access Agreement between BCH-1, Ltd. and U.S. Department of Energy. July 22, 2013
Institutional ControlsFlorida7/31/2013
4907-N01796_Sitewide semiannual dec12_may13
Sitewide Environmental Monitoring Semiannual Progress Report for the Young – Rainey STAR Center December 2012 Through May 2013. LMS/PIN/N01796 June 2013
Progress ReportFlorida6/28/2013
1 - 50Next
LM provides access to historical documents for our users' information and convenience.  Historical documents may contain links to outside sources. LM cannot attest to the accuracy of information provided by these links. Please see the  Privacy and Security page for more details.​ ​​Learn about the Department of Energy's Vulnerability Disclosure Program